A milestone in the construction of the £47m Long Stratton bypass has been reached after a new steel bridge over the route was hoisted into place.
The 42-metre long crossing was lifted into place - on top of specially constructed concrete abutments either side of the new road - using a 750-tonne crane.
Fabricated in Kent, the 90-tonne footbridge had to be delivered in two sections before it was welded together.
The bridge was delivered in two sections (Image: Drone Vision Norfolk)
Once complete and in use - by the summer - the footbridge will provide a walking and cycling route linking the existing public rights of way between Fairfield Close and Church Lane.
Grahame Bygrave, director of highways, transport and waste at Norfolk County Council said: "It’s fantastic to see the speed at which the new bypass is coming together and this is a really exciting step forward in its construction.
"The new road will reduce congestion in the town, benefitting local residents and our wider economy for years to come."
The new 2.4-mile bypass, due to open later this year, is being built by Octavius Infrastructure.
Jamie Harrison, the company's delivery director for highways, said: "I am pleased with the dedication of the team in achieving this important lift.
"It takes a high level of planning and collaboration between the factory and the site team to ensure a perfect fit.
"The project is currently progressing well in all areas and with the warmer weather approaching we remain confident of delivering everything on time."
The bypass will start at a new roundabout junction at Church Lane to the north and will re-join the existing A140 near Oakside Farm to the south.
The scheme is linked to plans for 1,800 new homes in fields on the edge of Long Stratton.