Motorists are warned to expect delays while work is carried out to repair Stone Road Bridge, north-west of Mattishall.

Work starts on Monday, February 27 and it will take five days to complete. Stone Road-Mattishall Road will be closed during this time.

The work involves repairing the damaged south-west brick parapet wall of the bridge, which is nearly a mile north of Yaxham Road.

The road is being closed to vehicles to provide a safe working area and conditions.

During the closure there will be a signed western diversion via Clint Green, Yaxham and the A47.

Access to properties and pedestrian access over the bridge will be maintained at all times.

The work, which will cost £5,000, will be carried out by Norfolk County Council's community and environmental services department and contractors.

The county council apologises for any inconvenience it may cause.