Beast from the East causes delay to opening of final stretch of NDR

PUBLISHED: 16:27 16 March 2018

The opening of the final NDR stretch has been delayed. Pictures: Andy Russell

The opening of the final NDR stretch has been delayed. Pictures: Andy Russell

Andy Russell

Council bosses say it is too early to say what the financial implications are of a missed week of work on the Norwich Northern Distributor Road due to the Beast from the East.

The final stretch of the NDR will open later than anticipated, after the Beast snatched away a week of work on it.

The forecasted completion date for the stretch connecting Wroxham Road to Postwick is now Thursday, April 5, falling just short of the goal of opening the road in its entirety before Easter.

The slight delay has come as a result of the Beast from the East’s impact on county roads, with the heavy snowfall preventing work from being carried out.

David Allfrey, highway and major projects manager for Norfolk County Council, said: “We lost the best part of a week’s work.

“It has taken a huge amount of effort to get it just to the stage we are now, but it is quite frustrating.”


If you value what this story gives you, please consider supporting the Eastern Daily Press. Click the link in the yellow box below for details.

Become a supporter

This newspaper has been a central part of community life for many years, through good times and bad, serving as your advocate and trusted source of local information. Our industry is facing testing times, which is why I’m asking for your support. Every single contribution will help us continue to produce award-winning local journalism that makes a measurable difference to our community.

Thank you.

Most Read

Most Read

Latest from the Eastern Daily Press